Hydro Power Development Master Plan

To prepare a master plan for least cost development of hydropower resources and prepare a detailed feasibility report for the first recommended project to enable UEB to initiate its construction by 1996/97.

Project ID
46002-P-UG-FAB-002
Activity status
3 - Completion
Aid type
C01 - Project-type interventions
% to Uganda
100.00

Organisations

Funding
African Development Fund
Extending
Government Of Uganda
Implementing
UGANDA ELECTRICITY BOARD

Disbursements by fiscal year, quarter

Fiscal year Fiscal quarter Value (USD) Uganda Value (USD)
2009 Q2 318,844.60 318,844.60

Commitments by fiscal year, quarter

Fiscal year Fiscal quarter Value (USD) Uganda Value (USD)
1993 Q2 928,279.07 928,279.07

MTEF projections by fiscal year

Fiscal year Value (USD) Uganda Value (USD)
1998 28,289.10 28,289.10
1997 69,270.79 69,270.79
1996 66,145.36 66,145.36
1995 64,733.53 64,733.53
1994 66,523.09 66,523.09
1993 41,511.78 41,511.78

CRS code %
Hydro-electric power plants (23065) 100.0