Hydro Power Development Master Plan
To prepare a master plan for least cost development of hydropower resources and prepare a detailed feasibility report for the first recommended project to enable UEB to initiate its construction by 1996/97.
- Project ID
46002-P-UG-FAB-002
- Activity status
- 3 - Completion
- Aid type
- C01 - Project-type interventions
- % to Uganda
- 100.00
Organisations
- Funding
- African Development Fund
- Extending
- Government Of Uganda
- Implementing
- UGANDA ELECTRICITY BOARD
Disbursements by fiscal year, quarter
Fiscal year |
Fiscal quarter |
Value (USD) |
Uganda Value (USD) |
2009 |
Q2 |
318,844.60 |
318,844.60 |
Commitments by fiscal year, quarter
Fiscal year |
Fiscal quarter |
Value (USD) |
Uganda Value (USD) |
1993 |
Q2 |
928,279.07 |
928,279.07 |
MTEF projections by fiscal year
Fiscal year |
Value (USD) |
Uganda Value (USD) |
1998 |
28,289.10 |
28,289.10 |
1997 |
69,270.79 |
69,270.79 |
1996 |
66,145.36 |
66,145.36 |
1995 |
64,733.53 |
64,733.53 |
1994 |
66,523.09 |
66,523.09 |
1993 |
41,511.78 |
41,511.78 |
CRS code |
% |
Hydro-electric power plants
(23065)
|
100.0
|