Bujagali Interconnection Project

Provide adequate transmission capacity for evacuation of power from Bujagali Power Station to one existing and future distribution companies, thereby increasing access to cheaper and more reliable electricity supply.

ID Projet
46002-P-UG-FA0-002
Statut de l'activité
3 - Completion
Type d'aide
C01 - Interventions de type projet
% to Ouganda
100.00

Organisations

Funding
African Development Fund
Funding
The Japan International Cooperation Agency/ Accelerated Cofinancing Facility for Africa
Implementing
UGANDA ELECTRICITY BOARD

Versements par exercice fiscal, trimestre

Exercice fiscal Trimestre fiscal Montant (USD) Ouganda Montant (USD)
2015 Q4 2,258.34 2,258.34
2015 Q2 623,541.13 623,541.13
2015 Q1 94,993.60 94,993.60
2014 Q3 275,931.99 275,931.99
2014 Q2 65,400.83 65,400.83
2013 Q4 4,373.85 4,373.85
2013 Q2 124,851.86 124,851.86
2013 Q1 151,425.08 151,425.08
2012 Q4 18,417.79 18,417.79
2012 Q2 53,149.24 53,149.24
2012 Q1 792,698.49 792,698.49
2011 Q4 190,902.99 190,902.99
2011 Q3 605,266.19 605,266.19
2011 Q2 630,355.55 630,355.55
2011 Q1 730,580.79 730,580.79
2010 Q4 701,490.18 701,490.18
2010 Q3 519,405.60 519,405.60
2010 Q2 313,466.93 313,466.93
2010 Q1 397,706.11 397,706.11
2009 Q4 784,387.96 784,387.96
2009 Q3 682,508.66 682,508.66
2009 Q2 4,194,044.96 4,194,044.96

Engagements par exercice fiscal, trimestre

Exercice fiscal Trimestre fiscal Montant (USD) Ouganda Montant (USD)
2007 Q2 26,105,693.90 26,105,693.90

Projections de CDMT par exercice fiscal

Exercice fiscal Montant (USD) Ouganda Montant (USD)
2012 2,116,426.08 2,116,426.08
2011 5,296,842.20 5,296,842.20
2010 5,253,904.98 5,253,904.98
2009 5,339,565.06 5,339,565.06
2008 5,438,952.33 5,438,952.33
2007 3,132,683.28 3,132,683.28

Code CRS %
(23010) 100.0